Orlando Health Sligh Medical Office Building
Sligh Medical Office Building and F Deck Parking Garage
Orlando, Florida

Orlando Health recently completed construction of a new medical office building with contiguous structural parking on the Downtown Orlando campus. The project was divided into two construction contracts—one for the parking garage and MOB structural shell and one for tenant improvements buildout.


Sligh MOB
F Deck Parking
Images courtesy of Finfrock

Features

  • Five-story, 54,669 square feet office build-out
  • Multi-tenant medical offices
  • Nine-level, 888-space parking garage

Project Team

  • Client Orlando Health
  • Architect Finfrock
  • Construction Manager Interstruct (TI Buildout)
  • Contractor Finfrock (Garage and MOB Shell)

Project Cost
$32 million

Project/Construction Start
April 2019

Completion Date
September 2020


ZHA staff provided Owner's Representative services including project management and system-wide team coordination with equipment providers and technical staff to successfully complete this project.

ZHA has worked as an extension of Orlando Health's Facilities Department staff since 2015 to provide oversight of project activities and communications to help deliver projects within schedule and budget guidelines.